Topic: | Re:Re:Re:high street flooeded | |
Posted by: | Matt Harmer | |
Date/Time: | 03/02/12 20:16:00 |
The latest update from Thames Water is as follows: The steel pipe in the bridge which connect the recently re-lined main was renewed five years ago however, one of this steel pipe joints just before the bridge has failed due to movement in the joint. A new joint with a modification has been ordered and it will be installed over the weekend. Thames Water is also using the road closure as an opportunity to replace a similar joint between the bridge and Augustus Close. The road is expected to re-open next Saturday 11th February 2012. |