There is also a consultation done and the plans were finally approved in 2019. These covered the stretch from Kew Bridge to Half Acre. The Pandemic struck and the budget disappeared, at least for a while. Details (a lot of them) here https://democraticservices.hounslow.gov.uk/mgAi.aspx?ID=111821#mgDocuments I believe all that is likely to proceed at present is from Kew Bridge to Watermans Park, which is expected in the spring. The next phase will be through to (the current) Morrisons but there is no programme at present, due to funding restrictions. |